正确认识家庭装修的装修顺序!

来源:http://www.jnjmzdc.com/添加时间:2019-04-02 10:56:19
对于新装修的房子,很多人都是迷茫的,不知道怎么开始。首先安排什么,然后做什么,往往是道听途说。今天为你列出装饰顺序。
  For newly decorated houses, many people are confused, do not know how to start. What is arranged first and then what is done is often hearsay. List the decoration order for you today.
  1、测量摸底。新房的设计必须根据自己的生活习惯,并对房间进行详细的测量,这一步绝不能偷懒。您以后需要掌握的尺寸和设计,包括家具风格定位等数据,都可以依靠这个预测量来提供。主要内容是每个房间的面积和墙壁的大小。这个区域要铺地砖还是木地板。它们能做造型吗?墙砖应选择多大尺寸?墙的大小决定了你想要选择的家具的大小,它是否可以放置,比例是否合适。
  1. Find out the measurement. New house design must be based on their own habits and habits, and a detailed measurement of the room, this step must not be lazy. The size and design you need to master in the future, including furniture style positioning and other data, can rely on this prediction to provide. The main content is the area of each room and the size of the wall. Are floor tiles or wooden floors to be laid in this area? Can they be modeled? What size should the tiles be? The size of the wall determines the size of the furniture you want to choose, whether it can be placed, and whether the proportion is appropriate.
  2、主体拆除与新建。在确定了设计方案之后,下一步是就是进入施工阶段了。此时,拆打是步,在那里需要拆打的墙壁,在那里需要增加新的墙壁,都需要在这一步完成。然而,在拆除和心建时,必须找出哪些是非承重墙,哪些是承重墙。你不能盲目地拆除。
  2. Main body demolition and new construction. After determining the design scheme, the next step is to enter the construction stage. At this point, demolition is the first step, where the walls need to be demolished, where new walls need to be added, all need to be completed in this step. However, in demolition and construction, we must find out which are non-load-bearing walls and which are load-bearing walls. You can't demolish it blindly.
  3、电工。在使用水和电之前,你需要做的就是确定你的家用电器的大小和你需要使用的电器的类型。例如,厨房是分体式灶或集成灶、电热水器和燃气热水器哪种选择。这些直接影响到在家中插座的位置和数量。在需要知道水电改造的路线以及位置,这些隐蔽项目需要在这类工作中进行。其次是第二次防水,但不要低估第二次防水,一定要做好,它在以后的生活中起着关键作用。
  3. Electrician. Before using water and electricity, all you need to do is determine the size of your household appliances and the type of appliances you need to use. For example, the kitchen is a separate or integrated stove, electric water heater and gas water heater which choice. These directly affect the location and number of sockets in the home. In need of knowing the route and location of hydropower transformation, these hidden projects need to be carried out in this kind of work. Second is the second waterproofing, but do not underestimate the second waterproofing, we must do a good job, it plays a key role in future life.
济南家庭装修
  4、砖工。砖工师傅的工作包括在房子的墙壁和地面铺设瓷砖,是否有补烂和拼花造型等。此时,你需要注意详细的马赛克设计图纸,以及地漏。因为地漏要由砖工和地砖一起安装。在铺砖之前,有必要确定用什么材料来填充房子里的下沉。如果是水泥板之类的,在铺设之前应该准备好。
  4. Brickmen. The masonry master's work includes laying tiles on the walls and floors of the house, whether there are patches and patchwork designs, etc. At this point, you need to pay attention to detailed mosaic design drawings, as well as floor drains. Because floor drains are installed by bricklayers and floor tiles. Before laying bricks, it is necessary to determine what materials are used to fill the sinking of the house. If it is cement slab or something, it should be ready before laying.
  5、木工。这个链接决定了家庭的设计效果。它主要包括家居的装饰天花板,一些定制的家具,以及墙壁的形状。如果新增了轻质隔墙等,都属于木工。此时,家庭厨房和浴室的天花板也可以同时建造。可经常有两种材料,铝制扣板天花板或石膏板天花板,现在木工师傅一般负责吊顶,家具都在市面上定做。
  5. Woodworking. This link determines the design effect of the family. It mainly includes the decorative ceiling of the home, some customized furniture, and the shape of the wall. If light partitions are added, they belong to carpentry. At this time, the ceiling of the family kitchen and bathroom can also be built at the same time. Often there are two kinds of materials, aluminium fastener ceiling or gypsum ceiling. Now woodworkers are generally responsible for ceiling, and furniture is customized on the market.
  6、灰工。灰工的主要工作是在家里的所有墙壁上,批量刮腻子,让墙面平整,刷表层乳胶漆。如果墙纸,只需粘贴墙纸的墙面进行基本处理。
  6. Grey workers. The main job of the gray workers is to scrape putty in batches on all the walls of the house, to make the walls smooth and to brush the surface with latex paint. If wallpaper, just stick wallpaper on the wall surface for basic treatment.
  7。安装木门和灯具。木门的尺寸可以定做,因为木门的生产工艺复杂,一般需要一个月,所以建议提前定做。后一步是安装灯的开关插座。所有这些工作完成后,家具和电器就可以进场了。
  7. Install wooden doors and lamps. The size of wooden doors can be customized, because the production process of wooden doors is complex, usually takes a month, so it is recommended to customize in advance. The last step is to install the switch socket of the lamp. When all this work is done, furniture and appliances can be brought in.

上一篇:济南家庭装修教你验收装修材料!
下一篇:新房打造榻榻米需要注意什么?

  • 公司名称:济南聚铭宅装饰有限公司   
  • 电话:13953144313  QQ:616391450   邮箱:616391450@qq.com
  • 地址:山东省济南市槐荫区刘长路国茂装材市场
  • [声明] 本站图片均由网站所有方提供,部分图片来源于网络,如有任何疑问请及时与我们联系,未经沟通本站不承担相关法律责任!